Barracuda Diving & Marine Service completed various marine works
Sep 2012 until Apr 2014
Works Completed at Aqaba New Port:
Welding piles underwater
Completed laying of the Intake Pipeline, from the sea to the chamber, including removal of the old pipeline and the connection between the old and new pipes. This was with double 250 m long and had a 30 degree bend – maintaining a minimal down time for Kemapco’s operations
Trained and experienced at placing X-blocks, a protective revetment, to high standards of design company’s requirements (see details here)
Welding Capping Beam Skirts to the steel tubular piles, an F4 (overhead) weld, with photo report of each and every weld
Anode installation
Slipway’s 60 meter underwater extension, earthworks prepared and screeding of gravel layer, leveling to high accuracy standards, underwater surveying, relocating the screeding frame, installation of foundation blocks and rail beams and bolting of rails to torque specifications
Dredging work underwater
Clearing debris from the seabed
Underwater inspections and reporting (including CCTV, Video & photos)
Lifting heavy objects from the sea
Installation and removal of silt curtains
Mason works, the process of placing gypsum underwater, fixing plywood and supervising the pouring of concrete between the capping beam skirts and the steel pile