Barracuda Divers Install Blocks At Al-hamriya Port

Al-hamriya Port for BAM International   

Barracuda Diving & Marine Service completed Breakwater Berth – placing blocks, screeding & geo-textile laying

Nov 15 – Feb 2016

Works Completed:

  • Breakwater Berth for the fishing port
  • Placing of blocks, that were 55 ton, around 2,000 pieces
  • Screeding, 854 meters
  • Geo-textile laying on the side of the back-fill

15 divers worked in 2 shifts, day & night from mid Nov 15 to mid Feb 16 to complete the job in the given time-frame.

 LINK to article in VIEW from BAM International at Al-hamriya Port (P9) 